Power-On Access to the A0 Photoinjector Cave
October 31, 2002
From time to time the Photoinjector operators wish to perform power on testing in the A0 photoinjector.
The photoinjector operators must complete a jumper request and complete a hazard analysis. The BD SSO and RSO must sign the paperwork as appropriate.
BD Radiation Safety must lock out with RSO locks both the 3 MW power supply and the 200 kW power supply. This ensures that it is not possible to produce x-rays inside the cave during the power on access. Photos are shown below.
|
||
3 MW Gun Klystron |
|
200 kW 9-Cell Klystron |
|
||
3 MW Gun Power Supply Lockout |
|
200 kW 9-Cell Power Supply Lockout |